Construction Scheme and Process Reference of 10000 Class Dustproof Chamber System
Release time:2019-08-22 source:
The premise of dust-free room construction is reasonable design. A perfect dust-free room construction scheme can make team operation more efficient. Ed Purification has sorted out the problems raised by many customers, and provided you with the construction plan of this dustless room, so that you can take a look at it as a reference.
I. Construction process of dust-free room system
1. The fresh air is mixed with the return air after filtering, and enters the air-cooled air conditioner. Through the medium-effect filter, the air which meets the requirements of temperature, humidity and cleanliness is sent into the dust-free room through the end low-resistance high-efficiency filter. The specific process is as follows:
2. Air distribution
(1) All of the 10,000 classes are provided with air return on both sides. In the workshop, pillar position and side wall are used as technical sandwich air return duct, which is connected with air return duct to air treatment unit. The air is sent to the clean room after being treated by coarse, medium and high-grade filters and temperature and humidity.
(2) The fresh air system carries out group, intermediate and secondary filtration to ensure the low dust concentration of air, reduce the influence of external dust sources, improve the purification effect of the dust-free room, and greatly prolong the service life of the high-efficiency filter and reduce the operation and maintenance costs.
(3) Fresh air volume is determined according to the requirement of sanitary fresh air (fresh air volume per person > 35m3/h) and the requirement of positive pressure in dust-free room. (Personnel less than 20)
3. System ventilation
Room ventilation with equipment and process requirements, such as this system, Party A's schemes.
II. Construction of Dustless Room
(1) Smallpox: Clean area and living area with double-layer high-quality thermal insulation (PU) color steel plate, dust-free and bright, grey color, 50 mm thick. It meets the requirements of cleanliness and antistatic of electronic workshop.
(2) Interval: Clean area and living area are protected and spaced by double-sided color steel insulation (PU) board.
Clean workshop space and ground and flower intersection to make arc and Yinjiao interface, dust-proof and easy to clean.
(3) Closed door: single door: 900 * 2000, glass observation window (same size of partition wall flat window), channel lock, door and door frame made of non-baking steel.
(4) Ground: Antistatic Specification
A. Cement floors in clean areas are treated to make 3mm anti-static epoxy floors. It meets the European EN548 standard and requirement. Fire protection performance conforms to: DIN4102-1,
Class B1: Anti-combustion in accordance with ISO06923: Flammability: Antistatic < +/-100V
Chemical resistance conforms to EM423: dilute acid resistance, grease resistance, and ethanol, acetone, stone-stained solvents, etc. It has the characteristics of no dust absorption and no dust absorption.
(5) Pillars: In the clean area, the pillars are completely edged with coloured steel plates and sandwiched with return air technology.
(6) Air shower room: According to the specifications, the air shower room of dust-free room is designed for two persons, two of them are:
3. Dust-free room lighting and distribution
Dust-proof lamp 40WX2 with cover for clean room (10,000 grade). Workspace illumination > 250 Lux,
The illumination of the aisle is more than 100 Lux. Local illumination can be used in areas with fine processing operation.
The wiring shall be carried out in accordance with the national norms and covered with threaded steel pipes, which conforms to the fire protection and power consumption norms. All pipelines should be well sealed through the clean area, and the inner holes (grooves) of the pipeline grooves should be fully sealed. The pipes and pipes entering the clean room should also be sealed, and the pipes that can walk on the roof should be set on the roof. Make the workshop clean and tidy.
Party A shall be responsible for all power distribution and sockets. The control box of purifying air conditioning system is in our charge.
Lighting and distribution are designed and manufactured according to the relevant national standards and Party A's requirements to meet the requirements of operation and control of equipment for students and management.
Example: Construction Scheme of Dustless Room
First, confirm the engineering design drawings and technical requirements before construction, and communicate with various specialties to discuss the problems that should be paid attention to in cross-operation. In engineering construction, the socket switch overlaps with the observation window due to the lack of timely communication with the electrical profession.
2. Check whether the main materials and equipment used in the project are qualified or not. If necessary, the owner shall be invited to participate in the inspection. Since the observation window is not inspected, the observation window is installed. The owner is not satisfied with the quality of the observation window after inspecting, which leads to the replacement and re-installation of the observation window.
3. Strengthen progress control and quality control during construction.
4. The construction management system of dust-free rooms should be strictly enforced.
Fifth, in the construction of the project, the material is first to the roof, then to the wallboard. However, the construction starts with the vertical wall panels, followed by the ceiling panels. Therefore, it leads to the contradiction between the demand for construction materials and the supply of materials.
On the sixth, second and third floors, many slabs are erected at the bottom of the floor girder. Because of the transportation and the overhanging of pipelines, the slabs are cut and used. The ceiling height can be ordered and then sealed with iron sheet between rooms.
7. The thickness of DC flat cement and PVC floor is not taken into account when the door is reserved, which results in friction between the bottom of the door and the floor after the installation of the steel door in the dust-free room.
8. After the installation of the air shower chamber, the wind speed of the air shower is small, which can not meet the requirements of the air shower. After many checks, it is the wrong phase sequence of the motor that causes the fan to reverse and the wind speed to be too small.
Ninth, the first floor of the board first arrival is some non-standard boards and standard boards according to the size of the drawings, the remaining large part is to be measured in the construction process of dimension processing. Because of the difference between the dimension of non-standard plate and the site and the lack of connection of non-standard plate, the alignment of plate joints and the lack of materials in the process of plate layout are caused, which ultimately leads to the construction progress is not obvious.
Ed Purification is a professional food aseptic workshop, GMP purification workshop, electronic dust-free workshop, food and pharmaceutical packaging workshop, medical equipment workshop, dust-free room, laboratory purification project design, construction, commissioning, installation.