Because the change of subjective and objective conditions is absolutely unchanged in the process of project implementation, while the relative imbalance is temporary and eternal in the process of project progress, the dynamic control of project objectives must be carried out in the process of project implementation with the change of the situation.
Comparing the planned and actual values of project objectives regularly in the process of project implementation, when it is found that the deviation of project objectives should be corrected in time, and at the same time, in order to avoid the deviation of project objectives to the greatest extent, active control measures should be taken, that is, pre-analysis of various factors that may lead to the deviation of project objectives, and effective pre-emption of these factors should be taken. Preventive measures.
1. Decomposition of Construction Progress Target of Purification Project Installation
1) The decomposition of the construction progress goal of the purification project is a process from macro to micro, from rough to fine, from the beginning of the installation and construction of the purification project and during the installation and construction of the purification project.
2) Dynamic tracking and control of the construction progress target of the installation of the purification project in the process of installation and construction of the purification project
According to the requirement of progress control, collect the actual value of installation and construction progress of purification project.
(2) Comparing the planned and actual values of the installation progress of the purification project regularly. According to the characteristics of the project, the schedule control period can be set as 10 or half months. When comparing the planned and actual values of the installation and construction progress of the purification works, we should pay attention to the corresponding engineering contents. For example, if the milestone events' progress target value or the refined progress target value are taken as the planned value of the progress, the actual value of the progress is relative to the milestone event or the actual progress of the further detailed work. The comparison of planned and actual progress values should be quantitative data comparison. The results of comparison are progress tracking and control reports, such as the preparation of ten-day, monthly, quarterly, half-year and annual reports of progress control.
(3) By comparing the planned value with the actual value of the installation progress of the purification project, if the deviation of the construction progress is found, the corresponding rectification measures must be adopted to rectify the deviation.
3) If it is necessary (that is to say, it is found that the original construction progress target of purification project installation is unreasonable, or that the original construction progress target of purification project installation can not be achieved, etc.), the construction progress target of purification project installation shall be adjusted.
(1) Decomposition of the construction cost target of purification project installation step by step. Through compiling the construction cost plan of purification project installation, the possibility of achieving the construction cost target of purification project installation is analyzed and demonstrated, and the construction cost target of purification project installation is decomposed.
(2) Dynamic tracking and control of the cost target of installation and construction of purification project in the process of installation and construction of purification project
According to the requirements of cost control, collect the actual value of installation and construction cost of purification project.
Edward purification has been developing for many years in the field of clean Engineering, and has implemented a series of workshop purification projects. For some difficult projects, it has also been through perfect technical strength and well-trained purification works. For more knowledge of medical purification industry, please pay attention to the public address: Aide-188 (Ed purify oxygen supply).