Construction process of plant purification workshop
Release time:2019-12-10 source:
I. construction preparation
1. Construction management department enters the construction site
2. Construction drawing handover meeting
3. Kick off site mobilization meeting
II. Wall structure installation
1. Setting out
2. Wall panel cutting
3. Wall panel installation
III. ceiling structure installation
1. Ceiling work
2. Ceiling hanging bar operation
3. Ceiling work completed
IV. installation of arc edge closing
1. Installation of inlay
2. Arc transition treatment
3. Edge closing operation completed
V. installation of ventilation system
1. Assembly of air duct
2. Air duct hoisting operation
3. Air duct installation in place
Vi. pipeline system installation
1. Piping edge pressing of water system
2. Water system pipeline construction
3. Completion of water system pipeline operation
VII. Installation of air conditioning equipment
1. Hoisting operation of air conditioner host
2. Install the air conditioner host in place
3. The air combined treatment unit is installed in place
VIII. Electrical system installation
1. Cable bridge construction
2. Electric box installation
3. Electric box installation in place
IX. floor decoration installation
1. The anti-static grid is laid
2. PVC ground construction
3. Electric box installation in place
X. system cleaning
1. Wall cleaning
2. Ground cleaning
3. Commissioning after cleaning
Xi. System commissioning and operation
1. Test run of air conditioner main unit
2. Water system commissioning
3. Trial operation of control system
XII. Project test and acceptance
1. Uniform detection of air volume at air outlet
2. Temperature, humidity and differential pressure detection
3. Noise and illumination detection