Management Requirements for Decoration and Construction Process of Purification Project
Release time:2019-08-19 source:
What are the management requirements for the decoration and construction process of the purification project? Ed Purification takes you to know about it.
First, confirm the engineering design drawings and technical requirements before construction, and communicate with various specialties to discuss the problems that should be paid attention to in cross-operation.
In engineering construction, the socket switch overlaps with the observation window due to the lack of timely communication with the electrical profession.
2. Check whether the main materials and equipment used in the project are qualified or not. If necessary, the owner shall be invited to participate in the inspection.
Since the observation window is not inspected, the observation window is installed. The owner is not satisfied with the quality of the observation window after inspecting, which leads to the replacement and re-installation of the observation window.
3. Strengthen progress control and quality control during construction.
4. The construction management system of clean rooms should be strictly enforced.
Fifth, in the construction of Century Star Project, the material is first to the roof, then to the wallboard. However, the construction starts with the vertical wall panels, followed by the ceiling panels. Therefore, it leads to the contradiction between the demand for construction materials and the supply of materials.
On the sixth, second and third floors, many slabs are erected at the bottom of the floor girder. Because of the transportation and the overhanging of pipelines, the slabs are cut and used. The ceiling height can be ordered and then sealed with iron sheet between rooms.
7. The thickness of DC flat cement and PVC floor is not taken into account when the door is reserved, which results in friction between the bottom of the door and the floor after the installation of the steel door in the clean room.
8. After the installation of the air shower chamber, the wind speed of the air shower is small, which can not meet the requirements of the air shower. After many checks, it is the wrong phase sequence of the motor that causes the fan to reverse and the wind speed to be too small.
Ninth, the first floor of the board first arrival is some non-standard boards and standard boards according to the size of the drawings, the remaining large part is to be measured in the construction process of dimension processing. Because of the difference between the dimension of non-standard plate and the site and the lack of connection of non-standard plate, the alignment of plate joints and the lack of materials in the process of plate layout are caused, which ultimately leads to the construction progress is not obvious.
Ed Purification is a purification engineering company specializing in the design, construction, commissioning and installation of food aseptic workshop, GMP purification workshop, electronic dust-free workshop, food and pharmaceutical packaging workshop, medical equipment workshop, laboratory purification and other projects. To learn more about the medical purification industry, please pay attention to the Wechat Public No. Aide-188 (Ed Purification and Oxygen Supply)