Construction process of color steel plate for Shandong purification
Release time:2019-10-08 source:
On the construction process of color steel plate:
Purifying color steel plate
1. On-site cleaning preparation: keep the construction area clean and tidy, the material stacking is concentrated, and the construction area is closed independently.
2. Datum line lofting (X Y Z axis point): According to the 1m line popping up on the column as the height datum line, the required height is measured. The mark of the elevation is designed by car as the Z axis height. The X/Y datum axis is determined according to the layout of the second design of the roof. The axis of the civil column is used as the datum line of the laying out, and it is used as the datum line of the construction of the metal wallboard for surveying and laying out.
3. Assembling and installation of aluminium profiles: install the assembly of adjustable ground rails according to the lay-out position on the ground. The ceiling assembly adopts all-wire suspender, T-nut, square regulator, link screw, etc. The connection between keel and suspender is fixed by T-screw. The hanger rod is fixed and locked in the groove of the C-type keel by screw.
4. Leveling and aligning bar elevation: using laser positioner to adjust and adjust on-site rail and ceiling regulator.
5. Aluminum profile fixing: After leveling horizontally, the upper and lower rails are locked with screws and the upper nuts of the regulator are locked.
6. Installation of color steel plate: the color steel plate seam is even and straight, the wallboard gap is not more than 3 mm, the roof gap is not more than 5 mm, the color steel plate must be flat, the surface smoothness is not more than 1 mm, the wall verticality is not more than 1 mm/1m; the roof must be installed strictly according to the design elevation, and the allowable deviation of the elevation is (+1 mm/1m).
7. Hand side of inner and outer arcs: no collision or scratch is allowed on the inner and outer arcs, and the flatness is not more than 1mm/1m.
8. Tearing and gluing: The protective film on the coloured steel plate is completely torn off and no residue is allowed; all seams are filled with sealant, and the sealant filling must be uniform, flat, smooth and one-time moulding.
9. Hygienic cleaning: After all working procedures are completed, a thorough hygienic cleaning will be carried out.
The purification project focuses on laboratory system engineering, medical purification engineering and clean workshop system engineering. With the relevant business qualification of the industry, from engineering consulting design, construction management, equipment and consumables supply, technical services, to laboratory certification, maintenance management, etc., to provide a comprehensive and complete solution for the medical purification engineering, laboratory system engineering, clean workshop system engineering industry. For more knowledge of medical purification industry, please pay attention to the public address: Aide-188 (Ed purify oxygen supply).