Several Key Factors in Operating Room Purification Project
Release time:2019-10-11 source:
Several key factors in the cleaning project of operating room:
I. Purification System
Indoor air purification system can be divided into horizontal laminar flow, vertical laminar flow and turbulent flow. The choice of air flow form can refer to the usual practice. Second, it depends on the working parameters of the room.
2. Cleanliness and ventilation times
The cleanliness of a room depends on the number of ventilations per unit time. Therefore, the working nature of the room and the requirements of production technology should be considered comprehensively, and then the technical parameters of the purification system should be determined.
3. Purification Engineering Structure
In order to ensure that the air flow is almost undisturbed, structural design must be carried out, and the necessary caution can prevent dust accumulation anywhere in the room.
IV. Design Scheme
In order to determine the design scheme, we must carefully consider the working nature of the room and the air flow conditions. Surface air supply should not be used in operating rooms with large dust emission. Operating rooms with high cleanliness requirements should be as far away from other operating rooms as possible.
V. Purification Materials
As the roof of clean room, the material of wall and floor must be not suitable for cracking, not easy to stain particles, and almost no dust. In addition, according to the different working conditions of the room, the chemical properties of the material must also be considered.
6. Pressure and airflow in operating room purification project
In order to ensure the cleanliness of the room, it is necessary to prevent polluted airflow from entering the room. To achieve this goal, positive pressure must be maintained in the room. In order to obtain the required room pressure, appropriate fresh air must be added.
VII. Purification Auxiliary Equipment for Operating Room Purification Project
When necessary, some auxiliary equipment should be installed in the operation room purification project, such as the air indicator of the fresh air outlet, the transmission window on the partition, etc. These devices must meet the requirements of the room, and they must really understand their functions.
VIII. Control of People and Things in Purification
People and objects are the main sources of dust in the clean room, so they must be fully controlled. For example, before entering the clean room, all people have to go through the clean system, change the dust-free clothes, and receive the basic education of the function of the clean system.
9. Water Supply, Drainage and Air Supply Devices and Power Supply for Operating Room Purification Project
Operating room purification project provides necessary water supply and drainage devices, air supply devices and power supply according to the operating room to be operated. These devices and related equipment must be easy to use and design, and must not be vigorous in the air purification system.
As a technical enterprise focusing on the design, research and development, construction and installation of operating room purification engineering in Shandong Province, Edward Purification has been steadfastly on the road of construction and development of operating room purification engineering. It is a trustworthy professional operating room purifier for domestic enterprises. For more knowledge of medical purification industry, please pay attention to the Wechat Public No. Aide-188. (Ed purifies oxygen supply)